Guides › Forecast your program's remaining budget
Guide · For program directors
Four numbers answer the question every program director gets asked: the budget, what has already been incurred, what is still coming, and what that leaves. This guide walks through each one, how to avoid counting a cost twice, and a worked example with sample figures.
Projected remaining = budget − (incurred + future). Incurred plus future is the projected total for the whole program period. If the projected total is higher than the budget, the remaining figure is negative and the program is on course to overspend.
Choose the date your records are complete through, usually the end of the last month whose payroll you have recorded. Everything on or before the cutoff is incurred, from your records. Everything after it is future, from your estimates. The same month is never counted both ways: once a month's payroll is recorded, that month stops using the staffing estimate.
Staffing is usually the largest line, so estimate it from the people on the plan rather than from last month's total:
Start and end dates matter as much as rates: a group leader who works 32 weeks of the school year costs nothing in July.
A purchase you have planned but not yet been invoiced for is a future cost. When its invoice arrives, the invoiced amount becomes incurred and only the rest stays planned, never both. Close a purchase when everything has arrived, or cancel it if it will not be bought, so it stops counting.
A program can be within budget overall and still be over in one category. Work out the remaining amount for each budget category as well as for the total. Then lay the projected costs out month by month: the running total as a share of the budget shows when the money runs out, not just whether it does.
It also helps to compare how much of each category has been incurred with how much of the program period has passed. That is a benchmark, not a target: costs are rarely spread evenly, and being behind can simply mean costs not yet recorded.
| Line | Amount |
|---|---|
| Budget for the program period | $308,110 |
| Incurred: invoices and recorded payroll through the cutoff | $23,853 |
| Future: staffing after the cutoff and open purchases | $208,231 |
| Projected total (incurred + future) | $232,084 |
| Projected remaining (budget − projected total) | $76,026 |
These are the synthetic figures of the sample after-school program in the Program Planner demo, where you can open each line to see the staff, invoices and purchases behind it.
A forecast is only as complete as the payroll you have recorded and the purchases you have planned; anything missing makes the remaining figure look better than it is. It is also not a funder's decision: a cost can fit the budget and still be disallowed, so check your award agreement and your funder's current fiscal manual.
Program Planner keeps one program's budget, staffing, invoices and projected remaining funds in one view, and recalculates when anything changes. Try it with sample data, no account needed.